Bridging the Gaps: New AMPP/NIA Mechanical Insulation Standards Aim for Industry-Wide Solutions

October 1, 2025

As work continues on the Association for Materials Protection and Performance (AMPP)/NIA mechanical insulation standards, a broad coalition of industry stakeholders—owners, engineers, contractors, manufacturers, and fabricators—are actively participating in an ambitious, essential goal: to create comprehensive, easy-to-understand installation standards that address the persistent gaps in current specifications.

To develop these standards, AMPP/NIA Standards Committee 27 leadership began by engaging with representatives from companies across the mechanical insulation supply chain to identify their pain points. Many of the pain points and challenges are outside
the insulation contractor’s direct control during installation of the insulation system, yet they determine the effectiveness of the system throughout its service life.

Physical and Field Installation Challenges

As confirmed in the pain points survey feedback, one of the most common issues involves inadequate pipe clearance and tight spacing. Pipes installed too close together not only make insulation application difficult but also may require the insulation thickness to be reduced. When there is adequate space to insulate a straight pipe, another pain point area is no space consideration for items such as flanges and valves. In both situations, the insulation contractor has limited options: thinner or no insulation on these items. In many cases, elbows, fittings, and clusters of components create congestion that hinders access. Engineering design must account for insulation thickness, ensuring that minimum spacing accommodates the combined insulation on adjacent pipes, valves, and flanges, plus an additional inch.

In addition, all insulated valves need to have actuator handle extensions longer than the thickness of the insulation. If the handle extensions are too short, then the only option is to install the insulation with a cutout so the handle can be used.

Another frequent problem is the use of incorrect or undersized support hangers, requiring the insulation to be altered. Supports that restrict proper insulation thickness can undermine system performance. Pipe supports should be sized to allow for the insulation to be continuous through the support.

Scheduling, Phasing, and Coordination

Beyond physical design and layout, scheduling and coordination are significant contributors to insulation failure. Installing insulation too early—e.g., before a building is fully enclosed, before pipe pressure testing, or before other trades have finished—exposes systems to moisture, which can cause mold and corrosion under insulation. Cold-weather conditions pose additional risks when mastics or caulks are applied below manufacturer-recommended temperatures.

Additionally, installing insulation while other trades are still working can lead to physical damage, as when ladders are leaned against the insulation, or workers tear off insulation when they need to access pipes for additional work.

Out-of-sequence work is another persistent challenge. Partial turnovers, staggered handoffs, and trade stacking often force insulation crews to work around incomplete systems or return for costly rework. An example of this is when drywall installation occurs before pipe testing and insulation, access is blocked, and timelines are disrupted.

Why These Problems Persist

Insulation contractors often point out that many of these issues need to be addressed by the mechanical contractor. While accurate in scope, the truth is that unresolved upstream problems will inevitably compromise the insulation system. Owners want durability, engineers want robust designs, and insulation contractors want effective installations, but non-insulation contractors may not prioritize or even understand the consequences of improper layouts and poor sequencing. Without consistent oversight, these problems are often noticed only after it is too late.

These concerns can be resolved easily during pre-installation planning; but once the system is in place, the effort and cost required to correct them grows exponentially.

A Practical Solution: Thermal Insulation Inspection

As is often emphasized in this magazine and throughout NIA messaging and education programs: Inspect what you expect. Inspection is critical in both initial installation and maintenance processes. Other trades—including welding, painting, electrical, plumbing, and HVAC—already have dedicated inspectors. The logical next step is the introduction of a thermal insulation inspector.

This inspector would participate in pre-job meetings, review contractor mobilization plans, and be present during critical phases of insulation installation. Their role would be to verify that preparatory work—pipe layout, supports, scheduling, and sequencing—is appropriate, and to assure that the insulation system is installed per the specifications. By identifying issues early, projects could prevent expensive rework, and facility owners would benefit from insulation systems delivering the intended performance over their full service life.

Conclusion

The path forward is clear: Establish well-defined standards, assign responsibilities appropriately across scopes, and provide dedicated oversight. With the AMPP/NIA standards effort now underway, and with genuine collaboration across trades, the mechanical insulation industry has an unprecedented opportunity to eliminate long-standing pain points. The result will be systems that are not only reliable and efficient, but also built to last.

Questions?

For more information about NIA’s insulation standards, please contact Kristin DiDomenico at kdidomenico@insulation.org, or visit www.insulation.org/nia-insulation-standards.

Jeff DeGraaf

Jeff DeGraaf’s extensive experience, leadership, and commitment to industry standards have made him a respected figure in the insulation community. With over four decades of national contracting experience, he continually drives advancements and is currently creating new national standards for the mechanical insulation industry as the Chair of AMPP/NIA Joint Standards Committee, SC 27 on behalf of NIA. DeGraaf currently serves as a Consultant for NIA, is a former member of NIA’s Board of Directors, a Past President of the Midwest Insulation Contractors Association (MICA) and served on MICA’s Board of Directors for 9 years. For 12 years, he has served on MICA’s Manual Committee, helping to develop and revise both the 8th and 9th versions of the North American Commercial and Industrial Insulation Standards manual, and the highly anticipated 10th edition scheduled for release in the spring of 2026. Previously, he was a Subject Matter Expert (SME) for NCCER, playing a key role in revamping their insulation class materials and tests.